Can I object to my neighbours' environment and planning permit?
If your neighbours are planning to renovate or demolish their property, they may need an environment and planning permit. If you disagree with this permit, you may submit a response or file an objection. You must have a valid reason for your objection.
Choose your situation:
My neighbours are applying for an environment and planning permit
If your neighbours still need to apply for the environment and planning permit, discuss the situation with your neighbours first. Perhaps you can find a solution together.
Announcement
When the municipality receives your neighbours' application, it must make this public. The municipality usually does this on its website or in the local newspaper.
Response
After the announcement, you can tell the municipality your opinion on the application by letter. This letter with your response is called a 'response'.
In the letter, explain why you disagree with the environment and planning permit for your neighbours. If your neighbours are following the building regulations with the permit, the municipality does not have to take your wishes into account.
My neighbours are getting an environment and planning permit
If you disagree with the municipality granting your neighbours an environment and planning permit, you may object within 6 weeks of the decision. The 6 weeks start when the municipality tells your neighbours that they have been granted the permit.
You can use our sample objection letter. In this letter, explain why you disagree.
You may only object if you are an interested party. For example, you live right next to your neighbours, or you look out onto the building site.
Please note
Valid reasons
The municipality may only withdraw the environment and planning permit for 'valid reasons'. This means that you must provide a good reason, for example:
- Your neighbours want to build something that does not fit in with the municipality's environment plan. An environment plan states what may be done with the land and buildings in a municipality.
- The construction does not follow building regulations, such as rules on safety, the environment or health, as stated in the Environment Buildings Decree (Bbl).
- The construction does not follow municipal building code. These are your municipality's rules for building, renovating, use and demolishing.
- The construction does not follow your municipality's aesthetic requirements. With these rules, the municipality determines what buildings can look like, for example, their shape or colour.
The court
If the municipality rejects your objection, you can disagree within 6 weeks. You file an appeal with the administrative court.
During the renovation
If your neighbours have started renovating or demolishing and they are not following the rules for the environment and planning permit, let your neighbours know. Perhaps they were unaware of this, and you can resolve the matter together.
You can also ask the municipality to do something about the situation. You can use our sample letter requesting the enforcement of building regulations. If your municipality does not respond within 8 weeks, you can issue them with a notice of default.
My neighbours are renovating without an environment and planning permit
Your neighbours may not need an environment and planning permit. If that is the case, you cannot object to the municipality.
If an environment and planning permit is needed, and your neighbours renovated anyway, or are still renovating without a permit, let your neighbours know. Perhaps they were unaware of this, and they can still do something about it.
You can also ask the municipality to do something about the situation. You can use our sample letter requesting the enforcement of building regulations. If your municipality does not respond within 8 weeks, you can issue them with a notice of default.
More information on this topic
Can my neighbours start building while the municipality is still deciding on my objection?
Can my neighbours start building while the municipality is still deciding on my objection?
Yes. Your neighbours can start building right after receiving the environment and planning permit. Your objection does not prevent this. Your neighbours do run the risk of having to stop construction if the municipality withdraws the permit.
Preliminary relief
If you want to prevent your neighbours from starting construction, ask the administrative court to stop the construction until the municipality has decided on your objection. This is called an 'application for preliminary relief'.
Where can I find information about permits that have been applied for and granted?
Where can I find information about permits that have been applied for and granted?
Your municipality must publish details of the permit applications it receives. For announcements, see, for example:
- your local newspaper or door-to-door newspaper
- your municipality’s website
- your municipality’s register, which records all permits applied for and granted
Your municipality does not have to publish the permits it has granted, but it often does.
What can I do about the nuisance caused by the renovation?
What can I do about the nuisance caused by the renovation?
If you cannot not stop the environment and planning permit, and you are experiencing nuisance because of the renovation, discuss this with your neighbours.
If you cannot find a solution, ask a neighbourhood mediator or mediator for help. They will help you and your neighbours find a solution together.